What each type of prototype proves, from proof of concept to pilot build, with lead times, a real nebuliser case and when a design is ready for tooling.
Summary
In its broadest sense, a prototype is any device that is not yet ready to be sold. Between the first idea and the first production unit, a product passes through several prototypes, and each should be built to answer specific questions. The types of prototyping available range from 3D printing and CNC machining to vacuum casting, soft tooling and production moulds, and each has its own limits on time, cost and how closely it represents the finished product. Choosing a prototype means balancing those trade-offs against the answers you need.
So the questions come first. Without them, any prototype risks being a waste of time and money, however good it looks on the bench. This guide covers physical products: electronics, mechanical hardware and medical devices. It explains what each type of prototype is for, which processes suit it, roughly how long it takes, and where medical device design controls come in, with one of our nebuliser projects as a worked example.
At MDS+ we group prototypes for a physical product into four types, usually built in this order. Each has a different job, and each is judged against a different question.
Naming varies between companies and industries, which causes confusion when a client, a design firm and a factory are all talking about the same build. This is how the common terms line up with ours.
| Prototype type | Other names you will hear |
|---|---|
| Proof of concept | Bench rig, breadboard, test fixture |
| ID model | Looks-like model, block model, appearance model, CMF model |
| Functional or engineering prototype | Looks-like-works-like prototype, EVT build (engineering validation test) |
| Pilot build | Production-intent or pre-production build, off-tool prototype, DVT and PVT builds (design and production validation tests) |
You will also hear “works-like prototype” for an early build that proves the function before the final form exists. It comes after the proof of concept and before the functional prototype.
In consumer electronics the later builds are usually called EVT, DVT and PVT, and some companies read the V as “verification” rather than “validation”. On a medical device, treat these as build names only. Design verification and design validation have specific meanings under medical device quality rules, which we cover further down.
The four types differ in the question they answer, how much of the final product they represent, and how long they take. The table sets them side by side.
| Prototype type | Question it answers | What it represents | Typical processes | Rough lead time | What you learn |
|---|---|---|---|---|---|
| Proof of concept | Does the core technology work as expected? | Function only, usually of one part of the device | 3D printing, CNC machining, breadboards, hand-wired modules | 2 to 6 weeks | Whether the principle is worth developing |
| ID model | Does the device look and feel right? | Form, size and finish, with no function | CNC machining | 3 to 4 weeks | Which look, feel and CMF direction to take forward |
| Functional or engineering prototype | Does it perform in its intended form, and is the design mature? | Form and function, with materials and finishes that approximate production | 3D printing, CNC machining, vacuum casting, soft tool injection moulding, rapid PCBs, bench assembly | 6 to 10 weeks per round | Device performance, and whether the design is ready for production tooling |
| Pilot build | Can the final design be built consistently, and does it pass verification and certification? | The final design, in production materials, on production tooling and assembly processes | Soft or hard tool injection moulding, production PCBs, SMD line, assembly line automation | 12 to 20 weeks for the first build | Design and process validation, certification results, user trial feedback |
Treat the lead times as a very rough guide. Each one covers design preparation (3D CAD files, 2D drawings with tolerances, and CMF specifications), part manufacturing, and device assembly, which may need its own jigs and fixtures. Device size and complexity move these numbers a lot. The first pilot build takes longest because it is the first time the production tooling and assembly line are used.
Each type has its own processes, lead time and limits. The limits matter as much as the purpose, because a prototype can only answer questions about the properties it actually represents.
A proof of concept answers questions about the core technology before money is spent on the rest of the device. We build it the cheapest and quickest way possible: off-the-shelf components, breadboards and hand-wired modules for the electronics, and 3D printed or CNC machined parts for the mechanics.
Clients often arrive having done this stage themselves. On the nebuliser project described below, the client had already tested the core technology with their own POC before we started.
What a POC cannot tell you matters just as much. It says nothing about form, how users will handle the device, how it will be manufactured or what it will cost to build. A working POC justifies the next round of spending, but it gives little indication of how close the product is to production.
An industrial design model is a non-functional model that shows the look and feel of the device: its size, proportions, how it sits in the hand, and its colour, material and finish. Holding a physical model settles questions that a rendering leaves open, and it gives the client and early users something real to react to.
We make ID models by CNC machining, then finish them to show the intended colour and surface texture. On the nebuliser project we produced several ID models so the client could choose the look and feel they wanted before the first functional prototypes were built.
CMF choices carry engineering consequences. The material and finish decide which manufacturing processes are possible and what each part costs, so we treat CMF as an engineering input from the first model.
A functional prototype, also called an engineering prototype, is a fully working device in the intended form. This is where we measure real performance and decide whether the design is mature enough to commit to production tooling.
The biggest influence on the process we choose here is material selection. 3D printing puts parts in your hands quickly and cheaply, but the printed material is often not representative of the final device material. It is also a family of processes rather than one, such as SLA, SLS and FDM, grouped under the standard term additive manufacturing in ISO/ASTM 52900, and each gives a different finish and strength.
Vacuum casting produces polyurethane parts in silicone moulds taken from a master pattern, using resins formulated to imitate production plastics. Soft tool injection moulding makes parts in the actual production resin, at a higher cost and with a longer lead time. CNC machining gives accurate parts in engineering materials, but the machinable grade and the machined surface can differ from the moulded part, as our nebuliser example shows. On the electronics side, rapid PCBs with bench assembly carry the early rounds.


We typically plan for two rounds of functional prototypes. The first round tests and refines the key functional characteristics. The second shows that the design is mature enough to commit to injection mould tooling.
Design for manufacture applies at this stage and at every other. A part made by 3D printing or CNC machining has to be designed for that process, and the design then changes when the next round moves to injection moulding. Each prototyping method has its own DFM rules, and the final manufacturing and assembly process has to be considered from the first design if the finished product is to reach the right balance of cost and performance.
A pilot build is the first time the device is made the way it will be made in production: the final design, production-intent materials, serial production tooling and the assembly line. Pilot units are used for full device verification testing, production process validation, certification testing and user trials, and they often serve as marketing samples too.
The processes are production processes: soft or hard tool injection moulding, production PCBs assembled on an SMD line, and assembly line automation where the line uses it. We typically plan for two pilot builds.
Pilot builds also expose problems that earlier prototypes could not show. By this stage, fixing them usually means changing production tooling, with a real cost in time and money. Our nebuliser example below is one of those cases.
Start from the question, then the properties the answer depends on, and only then the process. Four questions, asked in this order before any prototype is ordered, do most of the work.
The second question is the easiest to skip, and it is where spending more can save money. A 3D printed part is fine for checking fit or a first internal layout. It is the wrong choice when performance depends on the production material or surface. On our nebuliser project, moulding the functional prototype instead of machining it would have cost more and taken longer, but it would have exposed an aerosol impaction problem a full stage earlier, before the pilot tooling was made.
The decision that deserves the most care is committing to production tooling. A design should only reach that gate when the functional prototypes have shown it is mature, with materials and processes close enough to production that the results can be trusted. Making sure of that, and managing expectations along the way, is a large part of how we run rapid prototyping projects.
On a medical device, the prototypes that follow the proof of concept are normally built inside a controlled design process. The FDA has long said that design controls are not meant to cover concept and feasibility studies, and that as a rule of thumb they begin after feasibility, once the decision has been made to bring the device to market (FDA, CDRH Learn: Design Controls). In practice that puts the POC before formal design control, and the ID models, functional prototypes and pilot builds inside it.
The design and development requirements come from ISO 13485:2016, clause 7.3. Since 2 February 2026 they also apply in the US, because the FDA’s Quality Management System Regulation (QMSR) incorporates ISO 13485:2016 by reference, with some FDA-specific requirements kept on top. Four parts of clause 7.3 shape how prototypes are planned and used:
Risk management runs alongside all of this. ISO 14971:2019 applies to every phase of a device’s life cycle: identifying hazards, estimating and evaluating risks, controlling them and checking that the controls work. Each prototype round produces new evidence about hazards, so the risk file should change with it.
Usability follows the same pattern. FDA material on its human factors guidance allows early usability evaluations on mock-ups and prototypes, while the human factors validation test should use a device whose user interface represents the final design (FDA webinar on the human factors guidance). ID models and functional prototypes support the early work. The validation test belongs on pilot units.
This matters because poor design shows up later as field problems. A six-year FDA study of voluntary recalls (fiscal years 1983 to 1989) found that 44% could have been prevented with adequate design controls, and design is still cited as one of the most frequent causes of recalls (FDA, CDRH Learn: Design Controls).
Our nebuliser project is a typical example of the prototype route we apply. Each stage settled one decision before the next stage was paid for.
The pilot build performed worse than the functional prototype. The functional prototype parts had been CNC machined from a material similar to the final product’s. When the pilot units were tested, the different grade of material and the slightly different finish on the moulded parts produced more impaction of the aerosol than we had seen before.


If the functional prototype had been moulded instead of machined, it would have cost more and taken longer. The impaction issue would have shown up a stage earlier, though, and the change to the pilot tooling would have been avoided.
The lesson carries well beyond nebulisers. When performance depends on material grade or surface finish, the prototype has to represent that property, even when a cheaper process looks close enough.
The expensive mistakes tend to happen at the transitions, when a result from one type of prototype is trusted for a question it cannot answer.
There is often a gap in how the prototype process is understood, and the expectation is that once a 3D printed functional prototype works, the project is ready for mass production tooling. A printed prototype shows the function is possible. It says little about how the design behaves in moulded production material, or whether it can be moulded and assembled at all. Starting tooling before the design has been de-risked can have a significant impact on time and cost if changes are then needed.
NASA’s study of error costs on large hardware and software programmes gives a sense of scale: an error that cost 1 unit to fix at the requirements stage cost 7 to 16 units to fix during manufacturing, and 21 to 78 units during integration and test (NASA, Error Cost Escalation Through the Project Life Cycle). Device programmes are smaller than the spacecraft-scale systems NASA studied, so read those multipliers as an illustration of direction rather than a forecast.
When the answer depends on material grade or surface finish, a machined or printed part can give a confident result that later proves wrong, as it did on our nebuliser project.
DFM applies to every prototype stage, and each prototyping method has its own DFM rules. A design that has only ever been 3D printed will need changes before it can be moulded, and the final manufacturing and assembly process should shape the design from the first CAD model.
Without a written question there is no way to judge whether the prototype succeeded, and no basis for choosing its process, materials or quantity.
Prototype lead time also includes design preparation (3D CAD, 2D drawings with tolerances, CMF specifications) and assembly, which can need its own jigs and fixtures. Schedules that only count machine time come up short.
We typically plan for two rounds of functional prototypes and two pilot builds, adjusted for the complexity of the device. A plan with one functional round and one pilot build leaves no room for the changes those rounds exist to find.
It depends on the complexity of the device. As a starting point we plan for two rounds of functional prototypes and two pilot builds, then adjust for the device in question.
You can shorten a stage or combine questions, but the decision each stage settles still has to be made somewhere. A client who has already proven the core technology can start at ID models, as our nebuliser client did. The stage we advise against skipping is the functional round that shows the design is mature enough for production tooling.
As a very rough guide: 2 to 6 weeks for a proof of concept, 3 to 4 weeks for ID models, 6 to 10 weeks per round of functional prototypes, and 12 to 20 weeks for the first pilot build. Device size and complexity move these numbers a lot, and the total depends on how many rounds the device needs.
Cost depends on the type of prototype, the size and complexity of the device, the quantity, the processes and materials, and the finish required. A proof of concept is built as cheaply as possible, while pilot builds usually carry the largest cost because they need production tooling. The most reliable way to control cost is to match each prototype to the question it must answer, so you only pay for the realism that question needs.
A looks-like prototype shows the form, size and finish of a device without working. In our terms it is the ID model. A works-like prototype proves the function before the final form exists, and is built after the proof of concept. The functional or engineering prototype brings both together in one working device.
For fit checks, internal layout and early function, often yes. The printed material is often not representative of the final device material, though, so 3D printing is the wrong choice for tests where performance depends on material grade, surface finish or how a moulded part behaves.
From the first design. DFM applies at every prototype stage, each prototyping method has its own DFM rules, and the final manufacturing and assembly process has to be considered from the beginning to reach the right balance of product cost and performance.
For medical devices, design controls are generally not applied to concept and feasibility work such as a proof of concept. Once the decision is made to develop the device, the prototypes that follow sit inside the design and development process of ISO 13485, which the FDA’s QMSR has incorporated by reference since 2 February 2026. Design validation has to be done on representative product, such as initial production units, which in practice means pilot builds.
Jeff Mabbott
Director, Europe, MDS+
Jeff has more than 35 years in R&D, working as a design engineer, then a quality manager, then an industrialisation consultant. He has led numerous projects from proof of concept to mass production.
One message is enough to find out if we are the right fit for your hardware project.